Extension of the 11kV supply line from the detox area to the seepage well, including pole erection, a pole-mounted transformer and a DB shelter.

11kV Overhead Line Extension — photo 1

Germatek extended Adamus Resources' 11kV supply line from the detox plant to the seepage well. The work covered pole erection and dressing, conductor stringing, installation of a pole-mounted transformer, and the construction of a shelter for the distribution board at the well.

Scope of work

  • Pole erection and dressing
  • 11kV conductor stringing
  • Pole-mounted transformer installation
  • Distribution board and shelter
  • Testing and energisation